Third Party Quality Assurance Inspection of Hydronic Header and Pressure

Third Party Quality Assurance Inspection of Hydronic Header and Pressure

Quality Assurance of the hydronic header and pressure test for the system was verified. 80 psi was charged into the system 24 hours before inspection and the system held the pressure through the pour until the header was removed for reinstall in the finished mechanical room

Third Party Quality Assurance Inspection<< >>Mat Slab Concrete pour started

About the author : Net Zero Analysis & Design Corp.

Principal and CEO of Net Zero Analysis & Design Corp Passive House Consultant Energy Star Partner RESNET Quality Assurance Provider Building America Partner US DOE Zero Energy Ready Home Partner Member of the Board of Directors for BSI